As part of the road construction season, new asphalt was laid on 100 km of “Karaganda-Balkhash” road of republican significance. In addition, the number of special equipment and employees involved has been increased several times. Now 560 Nos. of special equipment and about 1 thousand road workers work at the facility.
By the end of the year, it is planned to close all bypass roads. A lot of work has been done on this part. Thus, the number of bypass roads has been reduced by 94%. If earlier the total length of bypass roads was 148 km, now it is only 9 km.
Let us recall that the total length of this road is 363 km, it consists of 8 sections. Construction and installation work continues.
In addition, this year, as part of a medium repair in Karaganda oblast, it is planned to put into operation about 70 km at three facilities. Namely, about 59 km on “Astana-Kabanbay Batyra-Nura-Temirtau” road (section from Nura village to Akmeshit village, km 101-128, 128-160) and 10 km on the road “Karaganda-Ayagoz— Bugaz-Tarbagatai” km 197-207 (Karkaralinsk-Matak section).