“Almaty – Khorgos” road construction progress

The length of "Almaty-Khorgos" road of "Western Europe - Western China" international transit corridor is 304 km. The road is constructed under technical category I with 4-lanes and cement concrete pavement.

Taking into account the traffic load on the existing road (Kuldzha tract), and lack of possibility to acquire land plots for the construction of roads in such towns as Guldana, Enbekshi, Baiterek, Avat, Baltabai, Aschysai and Taskensu, the design provides bypass of the settlements, and therefore 80% of road section will be constructed uner the new direction Almaty – Chilik - Charyn, which reduces the length of the route for 50 km and reduces the time for reaching the destination point.

Construction works on the section started in late 2013, involving the World Bank loan. The contract amount is 120 billion, of which 42,5 billion tenge disbursed up to day and it is planned to disburse 28.9 billion tenge this year.

Currently, work is being performed on 8 sections with the involvement of four General Contractors (JV "Dogus/Gulsan", JV "Todini/Kazakhdorstroy/ Impergilo", "Evrascon" and "OHL"). Works are performed by the joint venture "Dogus/Gulsan" on two sections, by joint venture "Todini/Kazahdorstroy/ Impergilo" on four sections, the construction of bridges and overpasses are being performed "Evrascon" and the bridge over the Ili river by "OHL". To date, works under construction of subgrade, subbase, base course and cement concrete pavement, construction of culverts and underpasses providing passage of special-purpose machinery are being carried out along the road.

3 thousand people, including 2.8 thousand people of local staff are involved in this project, and 1,195 units of road-building equipment, 10 cement plants and 8 crushing and screening plants have been mobilized.

Mainly materials of domestic production, which is over 90%, with the exception of metal structures of bridges and separate elements of furniture are used in the project.

Currently, 17.1 km cement concrete pavement, 28 km base and 3.9 million m3 subgrade, accounting for 75% of the total earthworks have been constructed under project.

In general, the works are being carried out in accordance with the approved work programs.

At the end of the year it is planned to open traffic on 150 km of cement concrete pavement in both directions.

 Navigation
 

 

 

«The completion of the Kazakhstan’s section of the Western Europe – Western China International Road Corridor is very important. It is really the construction of the century»

«We set an objective to develop infrastructure. And it turned out to be within our power. We are currently reviving the New Silk Road. We have opened access to the countries of the Persian Gulf and the Greater East. We have opened the Eastern gates, paving the way to the markets of China and the entire Asian continent», "Kazakhstan-2050” Strategy.
 
 
Address of the First President of the Republic of Kazakhstan – Elbasy, 2012.

 

 

 

 

«The executive authorities need a complete, high-quality Nurly Zhol Program. This is a strategic project which will affect the entire transport infrastructure».

 

 

 

 

 

Стратегия 2050

 

 

 

 

"WE-WC" projects
“Nurly zhol” projects
Procurements
Announcements
Press center
Multimedia
Questions & Answers Contacts