Question №362
April 13, 2015
Abylai Nurzhanovich | Shymkent

When Shymkent-Tashkent highway construction will be completed? And will Saryagach-Zhetysai road be repaired? The design contains Saryagach-Zhetysai road in both directions.

Answer to question №362
April 16, 2015

Dear Abylai, Shymkent-Tashkent road with the length of 101 km is divided into 3 sections. Work on the first section of 37 km is scheduled for completion at the end of 2015. Works on the remaining two sections have been commenced in March 2015 and it is scheduled for completion in late 2016. Saryagash – Zhetysai road is not a part of the "Western Europe - Western China" international transit corridor, and since our website is dedicated to this project, we can not give you answer under this issue.

 Navigation
 

 

 

«The completion of the Kazakhstan’s section of the Western Europe – Western China International Road Corridor is very important. It is really the construction of the century»

«We set an objective to develop infrastructure. And it turned out to be within our power. We are currently reviving the New Silk Road. We have opened access to the countries of the Persian Gulf and the Greater East. We have opened the Eastern gates, paving the way to the markets of China and the entire Asian continent», "Kazakhstan-2050” Strategy.
 
 
Address of the First President of the Republic of Kazakhstan – Elbasy, 2012.

 

 

 

 

«The executive authorities need a complete, high-quality Nurly Zhol Program. This is a strategic project which will affect the entire transport infrastructure».

 

 

 

 

 

Стратегия 2050

 

 

 

 

"WE-WC" projects
“Nurly zhol” projects
Procurements
Announcements
Press center
Multimedia
Questions & Answers Contacts