Question №362
When Shymkent-Tashkent highway construction will be completed? And will Saryagach-Zhetysai road be repaired? The design contains Saryagach-Zhetysai road in both directions.
Answer to question №362
Dear Abylai, Shymkent-Tashkent road with the length of 101 km is divided into 3 sections. Work on the first section of 37 km is scheduled for completion at the end of 2015. Works on the remaining two sections have been commenced in March 2015 and it is scheduled for completion in late 2016. Saryagash – Zhetysai road is not a part of the "Western Europe - Western China" international transit corridor, and since our website is dedicated to this project, we can not give you answer under this issue.