Question №141
February 08, 2012
Victor | Almaty city

- How do you do! Will you tell me, please, has the Main Contractor determined for construction of road section “Almaty-Khorgos” and “BACH”? If so, then which company is it? If not, then for what date has the Bidding procedure been determined?

Answer to question №141
February 09, 2012

Dear Victor, we give answer to all the items of your address. Project for reconstruction of highway “Almaty – Khorgos” will be implemented on account of loan of International Financial Institutions. At present procedures are conducted regarding attraction of loan, after which the Competitive Bidding will be conducted for determination of Contractor. In the Section “About Project” of our website you can familiarize with the scheme of the above road section. For all points regarding construction of the road “BACH”, we recommend you to apply to the official website of Almaty city.

 Navigation
 

 

 

«The completion of the Kazakhstan’s section of the Western Europe – Western China International Road Corridor is very important. It is really the construction of the century»

«We set an objective to develop infrastructure. And it turned out to be within our power. We are currently reviving the New Silk Road. We have opened access to the countries of the Persian Gulf and the Greater East. We have opened the Eastern gates, paving the way to the markets of China and the entire Asian continent», "Kazakhstan-2050” Strategy.
 
 
Address of the First President of the Republic of Kazakhstan – Elbasy, 2012.

 

 

 

 

«The executive authorities need a complete, high-quality Nurly Zhol Program. This is a strategic project which will affect the entire transport infrastructure».

 

 

 

 

 

Стратегия 2050

 

 

 

 

"WE-WC" projects
“Nurly zhol” projects
Procurements
Announcements
Press center
Multimedia
Questions & Answers Contacts