Printer-friendly versionPrinter-friendly version
Question №70
May 3, 2011
Talgat | Almaty city

- Good afternoon! Every year I and my family go for a holiday to the health resort “Saryagash” in South-Kazakhstan Oblast. Therefore, last summer I faced the problem, that diversion road, located in the area Kordai-Merke, is beneath criticism. Having arrived to Almaty, I had to repair undercarriage of my car. I would like to show my displeasure with the quality of pavement of the above diversion road. One can say that it is practically absent. I am planning a holiday in this health resort in the current year.
Based on the above, I would like you to answer my questions and appeal, as follows.
1. Why was the quality of the diversion road pavement not taken for control by relevant agencies?
2. I would like you to provide the detailed (scheme) information about planned diversions/ramps as per its status for the beginning of August 2011, informing at what road sections a new pavement will be available, and where it will not. I am concerned in the information about overall way from Almaty to Saryagash.
I will appreciate your reply at the earliest!

Answer to question №70

Dear Talgat. For your question, regarding the road condition and provision of runway from Almaty city to the health resort Saryagash, we inform you about the following.

Traffic will be carried out along the existing highway at the section from Almaty city to Kordai village.

Reconstruction of the road section is executed for the second technical category with two lanes between settlements Kordai and Kainar (km 210-262), traffic will be as follows. Traffic will be carried out along diversion road at the section from km 219 to km 239. For the rest of the sections the traffic will be carried out along new pavement and along existing road.       

is not thoroughfare for transit transport at the section Kainar-Oital (km 262-353), which is connected with the works executed for road reconstruction of the first category with 4 lanes. Traffic will be carried out along by-pass route Kainar-Shu-Oital: along the highways Shu - Blagoveshchenka (0-56 km) and Shu - Merke (7-97 km). 

Reconstruction works are executed for the first category with 4 lanes at the section Oital – border of South-Kazakhstan Oblast, and traffic will be carried out along new pavement and along existing road. Traffic will be carried out along diversion roads at the sections for construction of bridges, overpasses, culverts, as well as at the sections, where road alignment is executed. 

Further traffic will be carried out along the existing roads from the border of the region to the health resort “Saryagash”. 

 Navigation
 

 

 

«The completion of the Kazakhstan’s section of the Western Europe – Western China International Road Corridor is very important. It is really the construction of the century»

«We set an objective to develop infrastructure. And it turned out to be within our power. We are currently reviving the New Silk Road. We have opened access to the countries of the Persian Gulf and the Greater East. We have opened the Eastern gates, paving the way to the markets of China and the entire Asian continent», "Kazakhstan-2050” Strategy.
 
 
Address of the First President of the Republic of Kazakhstan – Elbasy, 2012.

 

 

 

 

«The executive authorities need a complete, high-quality Nurly Zhol Program. This is a strategic project which will affect the entire transport infrastructure».

 

 

 

 

 

Стратегия 2050

 

 

 

 

"WE-WC" projects
“Nurly zhol” projects
Procurements
Announcements
Press center
Multimedia
Questions & Answers Contacts