Question №511
August 26, 2018
Zhandos Seitkhanov | Taraz

Good afternoon. When will be opened two-way traffic on the section of Zhambyl region, from Blagoveschenka (turn on Shu) to Otar towards Almaty??

Answer to question №511
September 17, 2018

Dear Zhandos, as part of Uzynagash-Otar road reconstruction project a contract for construction and assembly work was signed on July 3, 2018 between the Committee of Roads and Kazakhdorstroy LLP section km 143-159.

Under section of the Zhambyl region, from Blagoveshchenka to Otar in the direction of Almaty, constrauction works is planned to be completed in 2020.

 Navigation
 

 

 

«The completion of the Kazakhstan’s section of the Western Europe – Western China International Road Corridor is very important. It is really the construction of the century»

«We set an objective to develop infrastructure. And it turned out to be within our power. We are currently reviving the New Silk Road. We have opened access to the countries of the Persian Gulf and the Greater East. We have opened the Eastern gates, paving the way to the markets of China and the entire Asian continent», "Kazakhstan-2050” Strategy.
 
 
Address of the First President of the Republic of Kazakhstan – Elbasy, 2012.

 

 

 

 

«The executive authorities need a complete, high-quality Nurly Zhol Program. This is a strategic project which will affect the entire transport infrastructure».

 

 

 

 

 