Question №476
You have informed in the answer to question 459, that it is planned to open traffic on "Shymkent-Tashkent" section, while to date there are sections without a hard coating, in some sections the second half of the road is not even started before the end of 2016. Why do you give not accurate and unreliable information? And when will the road be completed REALLY? The very route of WE-WC promised to finish in 2015, and now it is 2017. Herewith the President's words about the construction of 2,700 kilometers in 3 years you posted on the main page. Please provide real information.
Answer to question №476
Dear Mukhit, the traffic on "Tashkent-Shymkent" section was opened as scheduled, today there remain some works stipulated for in 2017, such as connection with the bridges, as well as pavement on culverts, and road furniture.
Regarding "Western Europe - Western China" project as a whole the works are completed, except for the section "Shymkent- Zhambyl oblast border" with the length of 37 km, where the work is complicated by construction of the tunnel. Work at this section is planned to be completed in late 2017.